Your Board of Directors had made the decision to replace eight exterior staircases in four buildings this year. COVID had set the manufacturing and delivery back but we have finally been given the delivery date for the first sets of exterior metal replacement stairs to replace the current metal stairs.
The first building to have the stairs replaced with be 2250. The parking lot side (B&C) will be replaced on Wednesday, December 16, and the backside stairs (F&G) will be replaced Tuesday, December 22.
THE RESIDENTS IN THE UPPER LEVELS WILL NEED TO VACATE THEIR UNITS WHILE THE WORK IS PROCEEDING. THERE WILL NOT BE AN EXIT OR ENTRY TO THE UPPER UNITS WHILE THE CURRENT EXTERIOR STAIRS ARE BEING REMOVED AND THE NEW STAIRS INSTALLED.
Please plan ahead to help minimize any inconvenience to yourself and family members, while your stairs are being removed and installed.
Weather permitting, Wednesday, December 16, JTR will be onsite with the first set of exterior metal replacement stairs for Building 2250 parking lot side (B&C)
Weather permitting, Tuesday, December 22, JTR will be onsite with the first set of exterior metal replacement stairs for Building 2250 parking lot side (F&G)
Please move your vehicles out of the 2250 parking lot to Benson Ave by 7:30 am on both Wednesday, December 16 and Tuesday, December 22. This includes vehicles in garages if you need to drive them on the noted days. If you have guests, this notice does apply also to them.
You can move your vehicles back onto the parking lot or garages after the crew leaves for the day, approximately 5:00 pm.
Subsequent stair delivery and install would follow for buildings 2254, 2262, 2284. Please watch for updates on the schedule for these installs.
1/12/2021
The next building scheduled to have the stairs replaced is 2254. The front side stairs (A, B, C, D) will be replaced Thursday, January 21.
RESIDENTS IN THE UPPER LEVELS WILL NEED TO VACATE THEIR UNITS WHILE THE WORK IS PROCEEDING. THERE WILL NOT BE AN EXIT OR ENTRY TO THE UPPER UNITS WHILE THE CURRENT EXTERIOR STAIRS ARE BEING REMOVED AND THE NEW STAIRS INSTALLED.
Please plan ahead to help minimize any inconvenience to yourself and family members, while your stairs are being removed and a new staircase installed.
Please move your vehicles out of the parking lot closest to the 2254 Building by 7:30 am on Thursday, January 21. If you have guests, this notice does apply also to them.
You can move your vehicles back onto the parking lot or garages after the crew leaves for the day, approximately 5:00 pm.
Subsequent stair delivery and install would follow for buildings 2254 rear, 2262, 2284. Please watch for updates on the schedule for these installs.
1/20/2001
As a reminder, the next building scheduled to have the exterior stairs replaced is 2254. The front side stairs (A, B, C, D) will be replaced TOMORROW, Thursday, January 21.
The rear stairs (E, F, G, H) are scheduled to be replaced next Thursday, January 28.
RESIDENTS IN THE UPPER LEVELS WILL NEED TO VACATE THEIR UNITS WHILE THE WORK IS PROCEEDING. THERE WILL NOT BE AN EXIT OR ENTRY TO THE UPPER UNITS WHILE THE CURRENT EXTERIOR STAIRS ARE BEING REMOVED AND THE NEW STAIRS INSTALLED.
Please plan ahead to help minimize any inconvenience to yourself and family members, while your stairs are being removed and a new staircase installed.
Please move your vehicles out of the 2254 parking lot and garages by 7:30 am on Thursday, January 21 and 28. If you have guests, this notice also applies to them. The 2254 garages may be blocked during the materials delivery and unloading of equipment. If you plan to use your vehicles that day, please remove vehicles from the garages and parking lot by 7:30 am.
You can move your vehicles back onto the parking lot or garages after the crew leaves for the day, approximately 5:00 pm.
Tentatively scheduled stair delivery and installs for the following buildings:
- 2262 Front Thursday, February 4
- 2262 Rear Thursday, February 11
- 2284 Front Thursday, February 18
- 2284 Rear Thursday, February 25
Please watch for updates and postings on the schedule for these installs. If there are changes to the schedule, you will be updated as soon as possible.
2/16/2021
The exterior stair install for 2262 Front (A, B, C, D) is scheduled for this Thursday, February 18, 2021 (weather permitting.)
Please plan ahead to help minimize any inconvenience to yourself and family members, while your stairs are being removed and new staircase installed.
For building 2262 front, the crew will be using the parking lot across from the 2276 garages.
Please move your vehicles out of the parking lot across from the 2276 garages and the 2276 garages if you plan to drive them that day by 7:30 am on Thursday, February 18. If you have guests, this notice does apply also to them.
You can move your vehicles back onto the parking lot or garages after the crew leaves for the day, approximately 5:00 pm.
3/3/2021
TOMORROW, Thursday, March 4 is the final stair install on the front of Building 2284 (A, B, C, D).
Please plan ahead to help minimize any inconvenience to your household while your stairs are being removed and new staircase installed.
The installation crew will park in the parking lot across from 2296 garages.
Please move your vehicles out of the parking lot across and garages on the dates and locations listed below if you plan to drive them that day by 7:30 am. If you have guests, this notice does apply also to them.
Social distancing is practiced with crew and residents for safety.
Thank you for all your patience and understanding while this project was in progress.
3/15/2021
We plan on continuing the exterior steel staircase installs with Building 2272 (A, B, C, D) side on Thursday, March 25. Followed by 2272 (E, F, G, H) on Thursday, April 1
Subsequent stair delivery and install would follow for buildings 2276, 2296 and 2310. Please watch for updates on the schedule for these installs.